How did we get here?

One of the most frequent questions we hear is “How did we get here?”

Below is a timeline for the Microsoft AI data centers and the We Energy Gas power plant

Kenosha County · Project history

Two projects.
One shared timeline.

Microsoft’s Kenosha data center and the Red Oak Ridge gas power plant, aligned by date.

Data center history compiled October 14, 2026. Gas plant history checked through October 19, 2026. Events appearing together show timing; they do not by themselves establish causation.

View sources
DateMicrosoft · Kenosha data centerRed Oak Ridge · Gas power plant
OCT 11, 2016
Data centerData center context

Boundary agreement announced

Paris, Somers and Kenosha announce a framework for I-94-area boundaries and sewer/water service. This is the land-use backdrop, not evidence Microsoft was involved then.

Sources: D1

No milestone listed in the source timeline.
NOV 10, 2017
Data centerData center official

State approves cooperative boundary plan

Wisconsin DOA approves the Kenosha–Somers–Paris plan. It creates growth areas and procedures for transferring Paris territory by attachment.

Sources: D2

Gas power plantBackground

Boundary agreement background

Paris places the preferred site in Kenosha/Somers growth areas under the 2017 agreement. This is land-use background; no plant approval occurred then.

Sources: G1

MAY 2024
Data centerData center reported

Kenosha signs NDA with Microsoft

Wisconsin Watch / WPR identify May 2024 as the signing month. The exact execution day, signatories and full terms have not been independently checked here.

Sources: D3

No milestone listed in the source timeline.
NOV 15, 2024
Data centerData center reported

Data-center proposal becomes public; operator unnamed

WGTD reports a roughly 243-acre, four-building campus at Burlington Road and 136th Avenue. The city cites an NDA while keeping the operator unidentified.

Sources: D4

No milestone listed in the source timeline.
NOV 21, 2024
Data centerData center official

Plan Commission hearing and 10–0 recommendation

Commission supports rezoning, an official-map change and a permitted-use amendment. Navix engineer Danielle Tatro says her client will remain unnamed until closing.

Sources: D5

No milestone listed in the source timeline.
NOV 21, 2024
Data centerData center official

Concept presented; neighbors can speak

Four buildings of 250,000 sq. ft. each, air-cooled chillers and a substation are discussed. Meredith Vandixhorn asks about access; John Holloway expresses support and notes Paris impacts.

Sources: D5

No milestone listed in the source timeline.
DEC 2, 2024
Data centerData center official

Council holds first readings

Attachment/classification, A-2 to M-2 rezoning and a permitted-use amendment advance. These are first readings, not the final December adoption.

Sources: D6

No milestone listed in the source timeline.
DEC 16, 2024
Data centerData center official

Attachment, rezoning and map actions adopted

Ordinance 52-24 attaches the Paris parcels; 53-24 rezones A-2 to M-2 Heavy Manufacturing; 54-24 changes permitted-use text. Resolution 174-24 updates the city map.

Sources: D7

No milestone listed in the source timeline.
DEC 16, 2024
Data centerData center official

Council hearing recorded; no speakers for or against

Minutes record no speakers at the grouped ordinance hearing. That does not mean no earlier participation: the November Plan Commission record contains public comments.

Sources: D7, D5

No milestone listed in the source timeline.
DEC 20, 2024
Data centerData center official

Ordinances published

Council minutes list December 20 publication for Ordinances 52-24, 53-24 and 54-24. Publication date is distinct from the December 16 vote.

Sources: D7

No milestone listed in the source timeline.
BY JAN 27,\n2025
Data centerData center official

Land acquisition announced; Microsoft publicly named

City/state announcement confirms approximately 240 acres purchased northwest of I-94 and Highway 142. Acquisition had occurred by this date; the individual deed closing dates remain to verify.

Sources: D8

No milestone listed in the source timeline.
JAN 29, 2025
Data centerData center reported

Purchase-price reporting appears

Business Journal reports $34.8 million / 233.5 acres; another report gives $34.16 million. Use approximately $34–35 million as reported, pending reconciliation against deeds and transfer returns.

Sources: D9, D10

No milestone listed in the source timeline.
JUL 25, 2025
No milestone listed in the source timeline.
Gas power plantFiled

Engineering plan filed

The utility acquisition application identifies July 25 as the original filing date. The preliminary plan describes five gas turbines and proposed and alternative sites.

Sources: G2, G3

AUG 6, 2025
No milestone listed in the source timeline.
Gas power plantGrid record

Grid interconnection request

MISO lists Red Oak Ridge as entry E0012: a gas simple-cycle project in Kenosha County with 1,186 MW requested capacity.

Sources: G4

SEP 9, 2025
No milestone listed in the source timeline.
Gas power plantOfficial letter

Somers president supports project

George Stoner writes the PSC supporting Red Oak Ridge and describes the preferred site as partly within the Somers growth area.

Sources: G5

NOV 5, 2025
No milestone listed in the source timeline.
Gas power plantFiled

Utility acquisition request

Wisconsin Electric applies to acquire and construct Red Oak Ridge, citing load growth and a very large customer seeking to subscribe. The proposed transaction is separate from construction approval.

Sources: G2

NOV 17, 2025
Data centerData center community

Opposition at Common Council

Residents filled the council meeting, seeking a halt to Microsoft’s proposal.

Sources: D11

No milestone listed in the source timeline.
NOV 25, 2025
No milestone listed in the source timeline.
Gas power plantOutreach

Local project presentation

The Town of Paris posts a presentation dated November 25, documenting local outreach before the formal December application.

Sources: G1

DEC 5, 2025
No milestone listed in the source timeline.
Gas power plantFiled

Construction application

PSC lists December 5 as the application date for docket 9837-CE-100. The project page describes up to 1,186 MW and an environmental impact statement process.

Sources: G6, G7

DEC 11, 2025
No milestone listed in the source timeline.
Gas power plantOutreach

Community open house

Invenergy advertises an open house where residents can view details and speak with its team.

Sources: G8

MAR 2026
Data centerData center official

Microsoft changes local-government NDA policy

Microsoft announces it will stop using local-government NDAs and coordinate termination of existing agreements. WPR reports the change March 20.

Sources: D13, D14

No milestone listed in the source timeline.
APR 2026
No milestone listed in the source timeline.
Gas power plantEnvironmental review

Draft environmental review

The PSC project page identifies an April 2026 draft environmental impact statement.

Sources: G7

MAY 2026
Data centerData center community

KUAMDC Public Museum town hall

A May 25 participant post reports a town hall held the prior weekend. Event is included with this evidence limit; the exact day needs an organizer record.

Sources: D15

No milestone listed in the source timeline.
JUN 22, 2026
Data centerData center reported

Kenosha NDA terminated

According to the city, as reported by WPR, Microsoft ends its Kenosha NDA. This is a local termination date distinct from the March policy announcement.

Sources: D16

No milestone listed in the source timeline.
JUN 26–30,\n2026
Data centerData center reported

Site plans awaited; Rhode Center forum held

WGTD reports the city awaits Microsoft site plans and an infrastructure development agreement. On June 30, KUAMDC co-sponsors the Rhode Center event with Charlie Berens.

Sources: D17, D18

No milestone listed in the source timeline.
EARLY JUL / JUL 1, 2026
Data centerData center community

Campaign visibility; separate Mount Pleasant lawsuit

User reports signs/social media increased after Rhode (unverified timing/scale). Sturtevant residents file a July 1 proposed class action over Mount Pleasant noise; this is not a Kenosha-site lawsuit.

Sources:

No milestone listed in the source timeline.
JUL 23, 2026
No milestone listed in the source timeline.
Gas power plantPublic participation

Public hearings and town comments

Paris posts two hearing recordings and its July 23 submitted letter.

Sources: G1

AUG 3, 2026
No milestone listed in the source timeline.
Gas power plantPublic participation

Written comments close

Paris lists August 3 as the written public comment deadline in the construction case.

Sources: G1

AUG 6, 2026
No milestone listed in the source timeline.
Gas power plantReported

Microsoft connection reported

Wisconsin Watch reports that Microsoft has signed up to purchase electricity from Red Oak Ridge. That does not establish a dedicated line to the Kenosha campus.

Sources: G9

AUG 27, 2026
Data centerData center reported

Residents press for moratorium; plans still developing

WPR reports KUAMDC’s push for a pause/referendum. City FAQ says site-plan process is required before permits; Microsoft says it will share more when a development plan is available.

Sources: D16

No milestone listed in the source timeline.
SEP 18, 2026
No milestone listed in the source timeline.
Gas power plantReview

Draft decision matrix

Paris posts a draft decision matrix dated September 18. The draft is not a final order.

Sources: G1

OCT 7–14,\n2026
Data centerData center community

Parkside forum; latest-status checkpoint

October 7 Parkside forum discusses jobs, utilities, water and accountability; FOX6 reports October 8. The source timeline was researched through October 14, 2026.

Sources: D20, D21

No milestone listed in the source timeline.
OCT 14, 2026
No milestone listed in the source timeline.
Gas power plantOfficial notice

County announces PSC meeting

Kenosha County announces the October 15 review and links final environmental impact statement materials.

Sources: G10

OCT 15, 2026
No milestone listed in the source timeline.
Gas power plantApproved with conditions

Conditional approval vote

PSC announces a conditional CPCN. Its release distinguishes the preliminary vote from the written Final Order, expected in coming weeks.

Sources: G11

Sources

D1 Town of Paris: boundary agreement history

D2 Wisconsin DOA: cooperative-plan approval, Nov. 10, 2017

D3 Wisconsin Watch / WPR: NDAs, Jan. 2026

D4 WGTD: proposal reported, Nov. 15, 2024

D5 City Plan Commission minutes, Nov. 21, 2024

D6 Common Council minutes, Dec. 2, 2024

D7 Common Council minutes, Dec. 16, 2024

D8 County/city-state acquisition announcement, Jan. 27, 2025

D9 Business Journal: land price, Jan. 29, 2025 (headline/preview)

D10 Milwaukee Daily Post: alternative price report, Jan. 29, 2025

D11 WISN: residents at council, Nov. 17, 2025

D12 PSC: Red Oak Ridge summary and case status

D12a PSC: application date / review status table

D13 Microsoft: decision to end local-government NDAs

D14 WPR: NDA policy change, Mar. 20, 2026

D15 Participant report: Museum town hall, posted May 25, 2026

D16 WPR: Kenosha project / moratorium report, Aug. 27, 2026

D17 WGTD: site plans still awaited, Jun. 26, 2026

D18 WGTD: Rhode Center event, Jun. 30, 2026

D19 WPR: Mount Pleasant lawsuit, Jul. 2, 2026

D20 Kenosha County Eye: Oct. 7 Parkside forum announcement

D21 FOX6: Parkside forum coverage, Oct. 8, 2026

G1 Town of Paris - project history, presentation, hearings and comment deadlines

G2 Wisconsin Electric - acquisition application, November 5, 2025 (pp. 10, 14, 24-25)

G3 Invenergy - preliminary engineering plan (pp. 1, 19; posted by Somers)

G4 MISO - ERAS interconnection requests, entry E0012

G5 Somers president - support letter, September 9, 2025

G6 PSC - highlighted construction cases, application date

G7 PSC - Red Oak Ridge project page and environmental-review links

G8 Invenergy - December 11, 2025 community open house

G9 Wisconsin Watch - Microsoft / We Energies contract reporting, August 6, 2026

G10 Kenosha County - October 14, 2026 meeting notice and FEIS links

G11 PSC - October 15, 2026 statement on conditional CPCN approvals